DETAILED PROJECT DESCRIPTION
LOCATION: CASCADE FALLS AREA
SITE PREPARATION $9,350.00 CONSTRUCTION COSTS $82,517.50 GENERAL CONDITIONS $26,673.50 OVERALL PROJECT COSTS: $118,541.00 Construction Detail:
40 TONS OF BOULDERS TO STABILIZE SOUTHERN EMBANKMENT FOR GATHERING AREAS ;
4′ WIDE SLATE TRAIL MIX PATH CONNECTING MAIN WATERFALL ENTRANCE AREA TO GATHERING AREAS AND OVERLOOK;
STONE BANDING AT LOOKOUT AREA;
42″ HT. FIELDSTONE RETAINING WALL AT OVERLOOK;
HANDRAIL AT OVERLOOK 35 LF;
MASONRY SLAB STONE STEPS INSTALLED TO CONNECT THE MAIN ENTRANCE OF WATER FALL AREA TO
3 BENCH INSTALLED
6 TRASH RECEPTACLE INSTALLED
3 EDUCATIONAL SIGNS INSTALL
TIMELINE
Month 1 (Preconstruction / Site Prep) DUR START DATE COMPLETION DATE Project Commencement 0d 25-Mar-24 10-Jun-24
Permit Issuance 12w 22-Jan-24 18-Mar-24
Order Material / Schedule labor 3d 19-Mar-24 22-Mar-24
Install Erosion Control/Tree Protection 2d 25-Mar-24 26-Mar-24
Clear & Grub 2d 26-Mar-24 28-Mar-24
Survey/Onsite Staking Layout: Overlook, Gathering Area, Sculpture House Area 1d 29-Mar-24 29-
Mar-24
Site Preperation Completion *first milestone* 3/29/2024
Rough Grading Walkways, Overlook 5d 1-Apr-24 5-Apr-24
Boulder Retaining Wall Installation at Overlook Areas 5d 8-Apr-24 12-Apr-24 Backfill & Grading at overlook Area 1d 12-Apr-24 12-Apr-24
Stone Step Instatllation at Pathways 10d 15-Apr-24 29-Apr-24
Footing Installation at Retaining Wall (Overlook) 2d 24-Apr-24 26-Apr-24 Retaining Wall Installation at Overlook 4d 30-Apr-24 3-May-24
Stone Banding Installation 4d 7-May-24 10-May-24
Slate Trail MixPathway Installation 5d 13-May-24 17-May-24
Client Walkthrough 1d 17-May-24 17-May-24
Hardscape Completion *second milestone* 5/17/2024
Concrete Pad / Trash Receptacle Installation 2d 20-May-24 22-May-24 Handrail Installation 3d 21-May-24 23-May-24
Bench Installation 2d 23-May-24 24-May-24
Fine Grade Lawn Area throughout / Seed & Straw 2d 22-May-24 24-May-24 Client Walkthrough 1d 24-May-24 24-May-24
Contingency / Weather Delays / Inspections 10d 27-May-24 10-Jun-24